Free Electrical Estimate Template & Generator
An electrical estimate on an older house is largely a set of assumptions about what sits behind the panel cover. This template records the existing service size, panel type, meter location and branch-wiring condition seen at the walkthrough, then prices the service upgrade, the circuits being re-landed, new circuits by count, and devices or fixtures as an owner allowance. Corrections that only surface once the dead front is off carry their own per-circuit and per-breaker rates.
PDF downloads cost $4.99 per document, or are included with Unlimited at $9/month.
One-time payment · No subscription
Create & preview free. Watermark-free PDF: $4.99 USD. No subscription required.
| Description | Qty | Rate | Amount |
|---|---|---|---|
| New branch circuits | 6 | $485.00 | $2,910.00 |
| Devices and trim | 22 | $78.00 | $1,716.00 |
| Permit and inspection allowance | 1 | $350.00 | $350.00 |
One-time payment · No subscription
Use-case checklist
What to include in a electrical estimate
A service upgrade is the one job where the customer has no power until you finish, which removes every chance to pause and renegotiate. If the estimate never recorded that the existing branch conductors are cloth-jacketed and brittle at the terminations, the six circuits that will not safely land on the new bus become an argument at four in the afternoon with the meter pulled and the utility already scheduled. A per-circuit correction rate published in advance moves that discovery onto one line. The other quiet cost is the inspection: anything the inspector calls for outside your written scope still has to be done before the utility will reconnect, and an estimate that does not say who pays for it has effectively said you do.
- existing service and panel assumptions
- circuit, device, and fixture quantities
- labor and material allowances
- permit, inspection, and patching responsibility
- code-correction and concealed-access exclusions
Example starting lines
| Description | Qty | Rate |
|---|---|---|
| New branch circuits | 6 | $485 |
| Devices and trim | 22 | $78 |
| Permit and inspection allowance | 1 | $350 |
Complete it cleanly
Record panel and service assumptions, circuit counts, device or fixture allowances, cable routes, patching responsibility, permit and inspection fees, and unit rates for code corrections discovered later.
How to make an electrical estimate in 6 steps
Open the estimate generator
Start from this page so the estimate opens with fields and sample lines already set up for electricians and electrical contractors. No account is needed to create or preview.
Enter both parties
Add your business name, address and contact details, then the customer name and address exactly as they should appear on the record.
Add the electrical lines
Replace each sample line with the real work or goods. Make sure the document shows existing service and panel assumptions, circuit, device, and fixture quantities, labor and material allowances.
Check the figures
Totals calculate as you type. Confirm quantities, rates, any tax line and the final total against your own records before you send anything.
Set the reference and dates
Give the estimate a unique number and the correct date so it can be traced later and matched to related documents.
Review and download the PDF
Record panel and service assumptions, circuit counts, device or fixture allowances, cable routes, patching responsibility, permit and inspection fees, and unit rates for code corrections discovered later. Preview is free; a PDF download costs $4.99, or is included with Unlimited.
Worked example
100 A fused service to 200 A, plus six kitchen circuits
Ferris Point Electric walked 27 Alder Street for the Nakamura family on Sept 12, 2026 ahead of a kitchen remodel. The house is a 1962 ranch on a 100 A fused service with an overhead drop to the west gable, and the walkthrough found cloth-jacketed branch conductors at several panel terminations.
- Existing condition recorded Sept 12: 100 A fused service, overhead drop, meter on the west gable, cloth-jacketed branch wiring brittle at six terminations
- findings only
- 200 A service upgrade: new meter main, 40-space panel, grounding electrode system and bonding, riser and weatherhead. Utility work at the pole is excluded
- $3,850.00
- Reconnect and re-land 18 existing branch circuits onto the new panel, including 6 replacement breakers where the old fuse-panel taps will not land
- $1,260.00
- Six new kitchen circuits per the remodel plan: two small-appliance, dishwasher, disposal, microwave, range, at $395.00 each installed
- $2,370.00
- Owner selection allowance, devices and fixtures: 24 devices with plates at $18.00 each and 8 recessed LED downlights at $115.00 installed
- $1,352.00
- One day of temporary power, utility disconnect and reconnect coordination, and one inspection standby appointment
- $560.00
- Permit and inspection fee allowance, paid to the jurisdiction and passed through at cost
- $385.00
- Estimate subtotal of priced scope
- $9,777.00
- Carried rates for corrections found once the dead front is off, billed only if performed: replacing a damaged branch conductor from panel to first box $185.00 per circuit, AFCI or GFCI breaker $78.00 each, each additional drywall opening for a fished run $60.00
- $0.00
- Estimate total as written, valid 30 days. Drywall patching and paint, appliance connection beyond the receptacle, utility company charges, and any work the inspector requires outside this scope are excluded
- $9,777.00
The figure that gets misread is the $1,260.00 to re-land 18 circuits, which prices moving sound conductors onto the new bus. Six brittle terminations were already visible on Sept 12, so name the per-circuit replacement rate on the estimate rather than discovering it with the meter pulled.
When this document is the right choice
Use this estimate to set a realistic expected cost before the final scope is known. An estimate is an informed approximation, not a final invoice. State the assumptions that could move the price and replace it with a quote or invoice once scope is confirmed.
Frequently asked questions
What should I write down about the existing panel before pricing a service upgrade?
Record the service size and whether it is fused or breakered, the panel manufacturer, the meter location and whether the drop is overhead or underground, the circuit count you will actually be moving, and the condition of the conductors at their terminations. Photograph the open panel on the walkthrough date and reference that date on the estimate. That record is what separates a condition that existed before you arrived from a condition the homeowner will later say your crew created.
How many inspection trips does a service upgrade need, and what should the estimate say about them?
Say how many are included and who has to be present. A panel swap is normally not energized again until the jurisdiction releases it and the utility reconnects, so that sequence, not your crew, sets the day the house has power back. This estimate prices one standby appointment inside the $560.00 coordination line and states that re-inspection trips are billed separately. The order of inspections, what the local inspector calls on a panel swap of this era, and the release process all differ by jurisdiction, so confirm the sequence with your authority having jurisdiction and write down the date you scheduled rather than promising the owner a turnaround.
Should utility company charges sit inside my number?
Keep them outside it and say so on the estimate, because you do not control them. Work at the pole, a service drop relocation, a new meter socket policy, or any connection or reconnection fee the utility assesses is typically billed by the utility to the account holder, and those tariffs and policies differ, so have the owner confirm theirs. Name who schedules the disconnect and reconnect, since that coordination is your labor and should be priced, as the $560.00 line does here. Tell the owner to expect a separate utility bill so a surprise charge does not read as something you concealed.
How do I keep a device and fixture allowance from swallowing my margin?
Put the unit basis on the line, not just a total. This estimate reads 24 devices with plates at $18.00 and 8 downlights at $115.00 installed, so an owner who selects $60.00 designer devices is looking at a per-unit difference of $42.00 across 24 openings, or $1,008.00, rather than arguing about a lump allowance. Say in writing that your markup applies to the difference exactly as it applies to base scope, and set a selection deadline tied to the rough-in date.
The customer wants a fixed price with no exclusions on a 1962 house. Is that realistic?
You can offer one, but you have to price the risk you are absorbing, and on an old service that premium is usually larger than the customer expected. The alternative worth offering is a fixed price for everything visible plus published rates for the specific unknowns, which is what this estimate does. Explain that the exclusions are not escape hatches but the three or four conditions a panel swap commonly uncovers, each with a rate they can read before anyone signs.